Limits to Growth Policy

Allocating Tofino’s Water Supply

On December 10, 2024, the District of Tofino Council adopted the Limits to Growth Policy, which is now in effect.

The policy is a measure from Council to assume a level of risk in order to prioritize the development of residential housing and developments from Tla-o-qui-aht First Nation.

The policy defines an upper limit on the allowable increase in water demand from the existing raw water supply. It establishes a framework for tracking new water usage and prioritizes specific types of development. By providing clear guidance and structure for development decisions, the policy ensures a predictable, consistent, and transparent approach to water resource management until an alternative water source is in place.

REMAINING WATER CAPACITY TRACKER

The overall remaining raw water supply to allocate towards new growth and development as of December 10, 2024, is 120 m3 /day.

Residential: 50 m3 | Commercial, Industrial, Institutional: 10 m3 | Tla-o-qui-aht First Nation: 60 m3

Overview

Background
Tofino’s water is collected with gratitude from the rainforests protected by Tla-o-qui-aht Tribal Parks in the Hahuulthii of the Tla-o-qui-aht Ha'wiih (chiefs). The community's water is drawn from five creeks on Meares Island, operating as a flow-through system.

In early 2024, the District received the Water Master Plan (WMP), which identified a deficit in Tofino's current raw water supply during the busy and dry months. A water deficit occurs when the community's Maximum Day Demand (MDD) exceeds the flow rate from the source creeks on Meares Island. Projections indicate that climate change, coupled with population growth, will heighten this supply shortfall, potentially leading to more days of heightened water restrictions in summer, impacting residents and visitors.

Based on recommendations from the WMP, the District is actively seeking to secure an alternative water source and additional treatment capacity by 2043. Until a secure alternative water source is established, interim measures are required to mitigate community impacts, which includes the Limits to Growth Policy.

Key Policy Information

  • All new developments must obtain a Water Allocation Certificate (WAC) before receiving a Building Permit. Allocated water supply will be tracked and deducted from the remaining raw water capacity.
  • The policy defines eligible and ineligible uses for water allocation.
  • Allocation of the remaining raw water supply will be managed on a first-come, first-served basis.

Frequently Asked Questions